Innovative Construction
MALAYAWATA STEEL BEHAD
Prai, Penang
See Thumbnails
click here

Construction and completion of the
substructure and superstructure works to the proposed No 2 Steel Making plant
and ancillary structures for Malayawata
Steel Berhad as the main general contractor
inclusive of
·
Civil works, inclusive road and drainage
·
Reinforced Concrete Structures 25,000
cum with the largest single pour at 500 cubic
meters
·
Structural Steel 6,500 tons
including 2,500 tons of Built Up sections
·
Architectural works
·
Civil construction included the
construction of a Ferro Alloy pit and a Sludge Pit of up to 12metere in
excavation in Marine Clay with a water table 300mm below ground level.
Contract is valued at RM 36 million
Duration of Project: 14 months
MALAYSIAN SHEET GLASS BERHAD

Proposed JB2F Plant on PLO 435, Zone II,
Mukim Plentong, District
of Johor Bahru, Johor for Messrs. Malaysian Sheet Glass Berhad.
This factory was constructed in Pasir Gudang under the
supervision of the clients representative and
Consulting Engineers Tahir Wong Sdn
Bhd of Kuala Lumpur.
We were the main contractors for this
Pilkington Float glass factory that included Site Preparatory work, Piling
and Substructure works, Reinforced Concrete and Steelwork and all
Architectural Finishes. Our scope of
work included the fabrication and installation of high value Furnace Support
Structural Steelwork.
Contract is valued at RM 25 million
Duration of Project: 11 months
NIPPON ELECTRIC GLASS (MALAYSIA) SDN BHD

Structural steel fabrication and
erection for Nippon Electric Glass Phase 4 & 5 - Kajima Corporation being
the main building contractors for this project.
1.
Structural Steelwork for NEG 3 2,500
tons
2.
Structural Steelwork for NEG 4 2,500
tons
3.
Structural Steelwork for NEG 5 700
tons
4.
Fast track project for Nippon Electric
Glass in Shah Alam.
Our scope included the procurement, fabrication drawing preperation, fabrication and erection of the plant
structure in this project.
Contract is valued at RM 7 million
Duration of Project: 4 months
Schutz-DSL Malaysia
Nilai, Negeri Sembilan



|